WHERE DO WE GO FROM HERE?

Decision whether to proceed by  Wedmore Parish Council Late 2016
2nd public event: feedback from the community on issues for inclusion in the Plan; design Survey Questionnaire Spring 2017
Questionnaire agreed and distributed to all parish households, with Housing Needs Assessment and ‘Call for Sites’ Summer 2017
Research Survey analysis complete, agreed by Steering Group and presented to WPC Early 2018
3rd public event: report back to Community Spring 2018
4th public event: Preferred Options consultation Autumn 2018
Draft Plan consultation Spring 2019
Submit to Sedgemoor DC/government (+ consultation) Summer 2019
Public Examination Autumn 2019
Referendum Early 2020
Plan adopted Summer 2020

Approximate time from ‘GO’ decision to adoption, three years + nine months